A 35 kV oil-immersed transformer connects utility, industrial and renewable-energy systems across a wide range of capacities. Because each project has different network and site conditions, the factory design should not start from voltage and kVA alone.
Clear technical data at the beginning reduces drawing revisions, protection changes and civil rework. The purchase specification should identify the guaranteed performance and the physical interfaces the supplier must meet.
Electrical Data That Drives the Design
Confirm rated power, frequency, primary and secondary voltage, highest system voltage, insulation level, vector group, neutral arrangement and tap range. The network study should provide the required impedance and short-circuit withstand duty.
Loss evaluation should distinguish no-load loss, load loss, auxiliary consumption and the economic value assigned to each. A low purchase price may not be the lowest lifecycle cost when the transformer is energized continuously.
Mechanical and Accessory Checklist
Define ONAN or ONAF cooling duty, temperature-rise limits and fan-control stages.
Confirm bushing type, terminal orientation, cable boxes or bus connections and phase spacing.
Specify conservator or sealed-tank arrangement, oil-preservation system and pressure protection.
List gauges, alarms, contacts, marshalling cabinet, CTs and online monitoring points.
Provide transport limits, lifting and jacking points, total mass and shipping configuration.
Coordinate foundation loads, oil containment, fire separation, earthing and maintenance clearances.
Approve Documents Before Materials Are Committed
The review package should include a general arrangement, nameplate data, terminal plan, control schematic, accessory list, foundation loads and guaranteed-loss schedule. Comments must be resolved consistently across electrical and civil drawings.
Factory test scope, witness points, report format and spare parts should be agreed before production. This keeps the final inspection focused on requirements that were defined, priced and engineered from the start.
Avant de définir les spécifications de votre projet, comparez les transformateurs à sec et à bain d’huile en termes de refroidissement, d’installation, d’entretien, de sécurité incendie, de rendement et d’application.
La modernisation d'un poste de distribution nécessite bien plus qu'une simple augmentation de la capacité des transformateurs. Les équipements doivent également garantir une conversion de tension stable, une maintenance prévisible et une intégration sécurisée aux systèmes de protection existants. Ce cas d'application présente...
Compact substations combine medium-voltage switching, a transformer and low-voltage distribution into a coordinated package. For renewable plants, factories and infrastructure sites, factory assembly can reduce field wiring and shorten the time be...
Artificial intelligence is moving from pilot projects into practical grid operations. The International Energy Agency’s September 2026 report Modernising Grids in the Age of Electricity says digital tools can improve forecasting, optimisation, sit...